February 24th, 2009-
Cypress Creek lot clearing began

July 2009-
Rough grading & stormwater completed

February 1st, 2010-
Water & Sewer completed

1

 

February 8th, 2010-
Construction began on units 5-8

 

 

 

1

 

February 22nd, 2010-
Curbing of roads began.

April 9th, 2010-
Curbing of roads complete.

 

 

1

 

April 4th, 2010-
Landscaping & irrigation for entrance begins.

 

 

 

1

 

April 30, 2010-
Landscaping & irrigation at entrance..

 

 

 

1

 

May 15 th, 2010-
Roads Paved

 

 

 

1

 

June 30th, 2010-
Units 5-8 completed (18,20,22,24 Cypress Circle)

 

 

 

1

 

August 23rd, 2010-
Units 39-44 Under construction

 

 

 

1

 

October 13th, 2010-
Units 57-60, 61-64 under construction,

 

 

 