Please join our Facebook page for current photos, updates & articles
Cypress Creek Updates
February 24th, 2009-
Cypress Creek lot clearing began
July 2009-
Rough grading & stormwater completed
February 1st, 2010-
Water & Sewer completed

February 8th, 2010-
Construction began on units 5-8

February 22nd, 2010-
Curbing of roads began.
April 9th, 2010-
Curbing of roads complete.

April 4th, 2010-
Landscaping & irrigation for entrance begins.

April 30, 2010-
Landscaping & irrigation at entrance..

May 15 th, 2010-
Roads Paved

June 30th, 2010-
Units 5-8 completed (18,20,22,24 Cypress Circle)

August 23rd, 2010-
Units 39-44 Under construction

October 13th, 2010-
Units 57-60, 61-64 under construction,